Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 2)

 

Environmental Permit no. EP-122/2002/D

 

Monthly Environmental Monitoring & Audit Report

 

-  JANUARY 2014 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

 

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

7 February 2014


Table of contents            

EXECUTIVE SUMMARY. 3

1      Introduction. 5

1.1        Scope of the Report 5

1.2        Structure of the Report 5

2      PROJECT BACKGROUND. 7

2.1        Background. 7

2.2        Scope of the Project and Site Description. 7

2.3        Project Organization and Contact Personnel 8

3      status of regulatory compliance. 10

3.1        Status of Environmental Licensing and Permitting under the Project 10

4      Monitoring Requirements. 11

4.1        Noise Monitoring. 11

4.2        Air Quality Monitoring. 12

5      Monitoring Results. 14

5.1        Noise Monitoring Results. 14

5.2        Air Quality Monitoring Results. 15

5.3        Waste Monitoring Results. 15

6      Compliance Audit. 17

6.1        Noise Monitoring. 17

6.2        Air Quality Monitoring. 17

6.3        Review of the Reasons for and the Implications of Non-compliance. 17

6.4        Summary of action taken in the event of and follow-up on non-compliance. 17

7      Cumulative Construction Impact due to the Concurrent
Projects
. 18

8      Environmental Site Audit. 19

9      Complaints, Notification of Summons and Prosecution. 20

10     conclusion. 21


lIST OF TABLES

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2012/08

Table 4.1      Continuous Noise Monitoring Stations

Table 4.2      Air Quality Monitoring Stations

Table 5.1      Continuous Noise Monitoring Stations for Contract no. HK/2012/08

Table 5.2      Air Quality Monitoring Station for Contract no. HK/2012/08

Table 5.3      Details of Waste Disposal for Contract no. HK/2012/08

Table 8.1      Summary of Environmental Inspections for Contract no. HK/2012/08

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 

 

 

LIST OF FIGURES

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 4.1         Locations of Environmental Monitoring Stations

 

 

 

lIST OF APPENDIces

Appendix 3.1    Environmental Mitigation Implementation Schedule

Appendix 4.1    Action and Limit Level

Appendix 4.2    Copies of Calibration Certificates

Appendix 5.1    Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2    Continuous Noise Monitoring Results and Graphical Presentations

Appendix 5.3    Air Quality Monitoring Results and Graphical Presentations

Appendix 6.1    Event Action Plans

Appendix 6.2    Notification of Exceedance

Appendix 9.1    Complaint Log

Appendix 10.1   Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report ¡V January 2014 specific for Environmental Permit no. EP-122/2002/D. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2011/07 ¡V Wan Chai Development Phase II and Central Wanchai Bypass ¡V Sampling, Field Measurement and Testing Works (Stage 2). This report presents the environmental monitoring findings and information recorded during the period of January 2014. The cut-off date of reporting is the last day of each reporting month.

 

  1. In the reporting month, the principal work activities of the contract are included as follows:

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

¡P                  Site preparation works

¡P                  Site survey

¡P                  Temporary works

¡P                  Stockpiling of fill materials

¡P                  Culvert K diversion

¡P                  Diaphragm wall preparation works

 

Noise Monitoring

  1. Continuous noise monitoring was conducted at ACL3 ¡V City Hall.
  2. There were four limit level exceedances recorded on 13 and 28 January 2014 during daytime in the reporting month. The exceedances were concluded as not project-related.
  3. Due to safety concern, the location of the continuous noise monitoring station at City Hall was finely adjusted to the roof of the City Hall, Low Block on 1 May 2013.

 

Air Quality Monitoring

  1. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted on every six days basis at ACL1 ¡V City Hall and ACL2a ¡V Contractor HK/2012/08 Site Office.
  2. Due to lack of electricity supply, the 24hr TSP at ACL2a was rescheduled from 20 Jan 2014 to 21 Jan 2014 and from 24 Jan 2014 to 25 Jan 2014.
  3. Due to the large scale renovation works at People¡¦s Liberation Army Headquarter, a Proposal for Relocation of Air Quality Monitoring Station at People¡¦s Liberation Army Headquarter (ACL2) was formally submitted to EPD on 4th November, 2013.
  4. Air Quality Monitoring at ACL2 was temporarily suspended during the period from 14th November, 2013 to 3rd December, 2013.
  5. The Proposal for Relocation of Air Quality Monitoring Station at People¡¦s Liberation Army Headquarter (ACL2) was approved by EPD on 27 November 2013.
  6. According to the approved proposal for relocation of Air Quality Monitoring station, the action and limit levels of ACL2a shall adopt the reference monitoring result from the baseline air monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.
  7. The air quality monitoring at ACL2a ¡V Contractor HK/2012/08 Site Office was commenced on 7 December 2013.
  8. No exceedances were recorded in the reporting month.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There was no environmental complaint received in this reporting month.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspection for Contract no. HK/2012/08 in this reporting period. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.

 

Future Key Issues

  1. In the coming reporting month, the principal work activities of the contract is anticipated as follows:

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

¡P          Concrete breaking

¡P          Stockpiling of fill materials

¡P          Culvert K diversion

¡P          Diaphragm wall preparation works

1          Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed take up the role as the Environmental Team (ET) under Environmental Permit no. EP-122/2002/D to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Central Reclamation Phase III - Studies, Site Investigation, Design and Construction (Register No.: AEIAR-040/2001) since 1 May 2013.

1.1.2.     This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-122/2002/D, during the period of January 2014. The cut-off date of reporting is the last day of each reporting month.

 

1.2          Structure of the Report

Section 1          Introduction ¡V details the scope and structure of the report.

 

Section 2          Project Background ¡V summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4          Monitoring Requirements ¡V summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5          Monitoring Results ¡V summarizes the monitoring results obtained in the reporting period.

 

Section 6          Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Site Inspection ¡V summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9          Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10        Conclusion

2          PROJECT BACKGROUND

2.1          Background

2.1.1       Central Reclamation Phase III - Studies, Site Investigation, Design and Construction (hereafter called ¡§the Project¡¨) are Designated Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central Reclamation Phase III - Studies, Site Investigation, Design and Construction (Register No. AEIAR-040/2001) has been approved on 31 August 2001.

 

2.2          Scope of the Project and Site Description

2.2.1.     The design and construction of Central Reclamation Phase III involves the permanent reclamation and construction and operation of a trunk road and its road tunnel that is shown at Figure 2.1.

2.2.2.     The key purpose of the study area encompasses the area of Victoria Harbour to the southeast of the new Outlying Islands Ferry Piers and north of Edinburgh Place and Lung Wui Road. The area extends eastward to Fenwick Pier Street and the Fleet Arcade, and includes the existing GPO, Star Ferry Piers, Queens Pier, City Hall, PLA Headquarters, Hong Kong Red Cross Headquarters building and the Tamar Site. The scope of the Central Reclamation, Phase III includes:

¡P          Reclamation and seawalls, roads and associated services, North Island Line Protection Works and Advance Trunk Road Tunnel (ATRT) for the CWB;

¡P          Reprovisioning of Star Ferry Pier, public landing steps, wallah wallah moorings, and motor boat/launch operators' kiosks;

¡P          External cooling water systems which consist of the cooling water pumping shells for future developments, and the reprovisioning of existing cooling water pumping stations and associated pipework systems and E&M works;

¡P          Reprovisioning of existing Leisure and Cultural Services Department (LCSD)'s facilities;

¡P          Provision of a flood relief path, stormwater culvert extensions, upgrading of hinterland stormwater drainage resulting from the reclamation, demolition of the existing waterfront structures and necessary landscaping;

¡P          The Hong Kong Station Extended Overrun Tunnel (EOT) and associated ventilation structures entrusted for construction within the CRIII works;

¡P          Reprovisioning of the Government Heliport at the Wan Chai PCWA and reprovisioning of the Wan Chai PCWA at Chai Wan Basin.

 

2.2.3.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the four individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

DP1

Central-Wanchai Bypass (CWB)

Schedule 2, Part I, A.7

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

DP3

Reclamation works

Schedule 2, Part I, C.1

DP4

The North Island Line (NIL) Protection Works within CRIII

Schedule 2, Part I, A.7

 

2.2.4.     The designated project work I (DP1) was awarded to China State-Leader Joint Venture HK/2012/08 as part of the Project works by the Civil Engineering and Development Department (CEDD). The construction work under Contract no. HK/2012/08 was commenced on 27 May 2013.

2.3          Project Organization and Contact Personnel

2.3.1       Civil Engineering and Development Department is the overall project controllers for the Central Reclamation Phase III Project. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

 

2.3.2       The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.2:

 

Table 2.2    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer¡¦s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer¡¦s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3922 3388

3912 3010

China State- Leader JV

Contractor under Contract no. HK/2012/08

Project Director

Mr. Andrew Tse

9137 1811

2877 1522

Project Manager

Mr. Victor Wu

9193 8871

Deputy Project Manager

Mr. Eddie Chung

9189 8118

Site Agent

Mr. Paul Lui

9095 7922

Environmental Officer

Mr. James Ma

9130 9549

Environmental Supervisor

Mr. Ching Man, Chan

6050 4919

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.3.3       In this reporting month, the principal work activities of the contract is included as follows:

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

¡P                  Site preparation works

¡P                  Site survey

¡P                  Temporary works

¡P                  Stockpiling of fill materials

¡P                  Culvert K diversion

¡P                  Diaphragm wall preparation works

 

2.3.4       In coming reporting month, the principal work activities of the contract is anticipated as follows:

Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West

¡P          Concrete breaking

¡P          Stockpiling of fill materials

¡P          Culvert K diversion

¡P          Diaphragm wall preparation works

 

3          status of regulatory compliance

3.1          Status of Environmental Licensing and Permitting under the Project

3.1.1.     A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1  Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-122/2002/D

1 Sep 2009

Valid

 

3.1.2.     The current status on licences and/or permits on environmental protection pertinent for contract no. HK/2012/08 showed in Table 3.2.

Table 3.2  Cumulative Summary of Valid Licences and Permits under Contract no. HK/2012/08

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Notification of Works Under APCO

355439

4 Feb 2013

N/A

Valid

Registration as a Chemical Waste Producer

5213-134-C3790-01

8 Mar 2013

N/A

Valid

Billing Account under Waste Disposal Ordinance

7016883

18 Feb 2013

18 Jul 2017

Valid

Construction Noise Permit (if any)

GW-RS1357-13

2 Dec 2013

4 Dec 2013 to 1 Jun 2014

Valid

 

3.1.3.     Implementation status of the recommended mitigation measures during this reporting month is presented in Appendix 3.1.

 

4          Monitoring Requirements

4.1          Noise Monitoring

NOISE Monitoring Stations

4.1.1.     The continuous noise monitoring station for the Project is listed and shown in Table 4.1 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.1    Continuous Noise Monitoring Stations

District

Station

Description

Central

ACL3

City Hall

 

Noise Monitoring Parameters, Frequency and Duration

4.1.2.     Continuous 24-hour noise monitoring shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 hours daily basis when noise generating activities are underway:

¡P          One set of measurements between 0700 and 1900 hours on normal weekdays.

¡P          One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

¡P          One set of measurements between 2300 and 0700 hours on next day on every day.

4.1.3.     If construction works are extended to include works during the hours of 1900 ¡V 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

4.1.4.     As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agrees to within 1.0 dB.

4.1.5.     Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

4.1.6.     The sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency before deployment to the site and during each site visit. Measurements will be accepted as valid only if the calibration level from before and after the noise measurement agrees to within 1.0 dB.

4.2          Air Quality Monitoring

Air Quality Monitoring Stations

4.2.1.     The air quality monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.2    Air Quality Monitoring Stations

Station ID

Description

ACL1

City Hall

ACL2a

Contractor HK/2012/08 Site Office

Air QUALITY Monitoring Parameters, Frequency and Duration

4.2.2.     One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

4.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

4.2.4.     For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

4.2.5.     High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

¡P          0.6 ¡V 1.7 m3 per minute adjustable flow range;

¡P          Equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

¡P          Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

¡P          Capable of providing a minimum exposed area of 406 cm2;

¡P          Flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

¡P          Equipped with a shelter to protect the filter and sampler;

¡P          Incorporated with an electronic mass flow rate controller or other equivalent devices;

¡P          Equipped with a flow recorder for continuous monitoring;

¡P          Provided with a peaked roof inlet;

¡P          Incorporated with a manometer;

¡P          Able to hold and seal the filter paper to the sampler housing at horizontal position;

¡P          Easily changeable filter; and

¡P          Capable of operating continuously for a 24-hour period.

 

4.2.6.     Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

Laboratory Measurement / Analysis

4.2.7.     A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

4.2.8.     Filter paper of size 8¡¨ x 10¡¨ shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

4.2.9.     After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

4.2.10.   All the collected samples shall be kept in a good condition for 6 months before disposal.

4.2.11.   Current calibration certificates of equipment are presented in Appendix 4.2.

5          Monitoring Results

5.0.1.     The environmental monitoring will be implemented based on the division of works areas of each designated project managed under different contracts with separate FEP applied by individual contractors.  Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual Contract(s).

5.0.2.     In the reporting month, the concurrent contract is:

Ÿ  Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai West.

5.0.3.     The environment monitoring schedules for reporting month and coming month are presented in Appendix 5.1.

5.1          Noise Monitoring Results

5.1.1       Due to safety concerned, the location of the continuous noise monitoring station at City Hall was finely adjusted to the roof of the City Hall, Low Block on 1 May 2013.

5.1.2       The proposed division of noise monitoring stations is summarized in Table 5.1 below.

Table 5.1    Continuous Noise Monitoring Stations for Contract no. HK/2012/08

Location ID

District

Description

ACL3

Central

City Hall

Remarks: Continuous noise monitoring results and graphical presentation for ACL3 during restricted hours and night time period are for information only.

5.1.3       There were four limit level exceedances recorded at ACL3 - City Hall during daytime on 13 and 28 January 2014 in the reporting month. The exceedances were concluded as not project-related.

5.1.4       On 13 Jan 2014, after checking work activities of contractor HK/2012/08, it was found that no major noisy activities were performed during the recorded period. Flag raising ceremony near the lower block of City Hall was observed on 13 Jan 2014. As the exceedances were non-continuous, they were considered as non-project related and contributed by the ceremony and nearby traffic.

5.1.5       On 28 Jan 2014, after checking work activities of contractor HK/2012/08, it was found that no major noisy activities were performed during the recorded period. Lifting works for City Hall's renovation were observed during the monitoring period and the exceedance was not continuous. As such, the exceedance was not contributed by Project works and considered as non-project related.

5.1.6       Continuous noise monitoring results measured in this reporting period are reviewed and summarized. Details of continuous noise monitoring results and graphical presentation can be referred to Appendix 5.2.

5.2          Air Quality Monitoring Results

5.2.1       The proposed division of air quality monitoring stations are summarized in Table 5.2 below.

Table 5.2    Air Quality Monitoring Station for Contract no. HK/2012/08

Station

Description

ACL1

City Hall

ACL2a

Contractor HK/2012/08 Site Office

 

5.2.2       Due to lack of electricity supply, the 24hr TSP at ACL2a was rescheduled from 20 Jan 2014 to 21 Jan 2014 and from 24 Jan 2014 to 25 Jan 2014.

5.2.3       Due to the large scale renovation works at People¡¦s Liberation Army Headquarter, a Proposal for Relocation of Air Quality Monitoring Station at People¡¦s Liberation Army Headquarter (ACL2) was formally submitted to EPD on 4th November, 2013.

5.2.4       Air Quality Monitoring at ACL2 was temporarily suspended during the period from 14th November, 2013 to 3rd December, 2013.

5.2.5       The Proposal for Relocation of Air Quality Monitoring Station at People¡¦s Liberation Army Headquarter (ACL2) was approved by EPD on 27 November 2013.

5.2.6       According to the approved proposal for relocation of Air Quality Monitoring station, the action and limit levels of ACL2a shall adopt the reference monitoring result from the baseline air monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.

5.2.7       The air quality monitoring at ACL2a ¡V Contractor HK/2012/08 Site Office was commenced on 7 December 2013.

5.2.8       No action or limit level exceedance was recorded at ACL1 ¡V City Hall and ACL2a ¡V Contractor HK/2012/08 Site Office in the reporting month.

5.2.9       The air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 5.3. 

5.3          Waste Monitoring Results

5.3.1       Only non-inert C&D wastes were disposed in this reporting month. Details of the waste flow table are summarized in Table 5.3.

 

Table 5.3    Details of Waste Disposal for Contract no. HK/2012/08

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

288

TM38

Inert C&D materials recycled, m3

NIL

NIL

NIL

Non-inert C&D materials disposed, m3

15

110

SENT Landfill

Non-inert C&D materials recycled, m3

NIL

NIL

NIL

Chemical waste disposed, kg

NIL

NIL

NIL

 

6          Compliance Audit

6.0.1.     The Event Action Plan for construction noise and air quality are presented in Appendix 6.1.

6.1          Noise Monitoring

6.1.1.     No exceedance was recorded at ACL3 ¡V City Hall in this reporting month.

6.2          Air Quality Monitoring

6.2.1.     No action or limit level exceedance was recorded at ACL1 ¡V City Hall and ACL2a ¡V Contractor HK/2012/08 Site Office in this reporting month.

6.3          Review of the Reasons for and the Implications of Non-compliance

6.3.1.     There was no non-compliance from the site audits in the reporting period. The observations and recommendations made in each individual site audit session were presented in Section 8.

6.4          Summary of action taken in the event of and follow-up on non-compliance

6.4.1       There was no particular action taken since no non-compliance was recorded from the site audits in the reporting period.

 

 

 

7              Cumulative Construction Impact due to the Concurrent Projects

7.0.1.     This section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East (CWB Tunnel).

7.0.2.     According to the Monthly EM&A report (December 2013) of Central Reclamation Phase III (CRIII) for Contract HK 12/02, installation of directional sign at Road P2, removal of two existing E&M drawpits at East Bound Road P2 near Road D8 and additional surface drain at ACL CER office compound were performed in January 2014 reporting month. The water quality monitoring was completed in October 2011 and no Project-related exceedance was recorded for air and noise monitoring.  It can be concluded that cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) undertaken by contractor HK12/02 was insignificant.

7.0.3.     According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activity under Wan Chai Development Phase II were marine works at HKCEC areas, cross-harbour Watermains, Fresh Watermains and Cooling Watermains Installations, tunnel works at Wan Chai East. The major construction activities under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were tunnel construction at TS4 and tunnel construction and dismantling of struts at TPCWAE. Bridge construction and tunnel works at Central Interchange, ELS segment launching works and IEC parapet demolition at North Point area. The major environmental impact was water quality impact at Causeway Bay and Wan Chai. Land-based construction activities were tunnel works at TS2, ELS work and tunnel construction at TS4 and tunnel construction and dismantling of struts at TPCWAE, tunnel works at Central and ELS work at North Point and tunnel works at Wan Chai East in the reporting month.

7.0.4.     The major environmental impacts generated from tunnel works at Central and tunnel works at Wan Chai East, IECL and Causeway Bay Typhoon Shelter were undertaken in the reporting month. No significant air impact from construction activities was anticipated in the reporting month. Besides, no project-related exceedances were recorded during the air and noise environmental monitoring events in the reporting month. Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Wan Chai Development Phase II was insignificant.

8          Environmental Site Audit

8.0.1.     Four site inspections for Contract no. HK/2012/08 were carried out on 7, 14, 21 and 29 January 2014 in the reporting month. The results of the inspection and outcome are summarized in Table 8.1.

Table 8.1    Summary of Environmental Inspections for Contract no. HK/2012/08

Item

Date

Observations

Action taken by Contractor

Outcome

140114_01

14-Jan-14

Open stockpile should be covered properly or provided with water spraying.

Stockpiles were covered.

Completion as observed on 21 Jan 2014

 

 

9          Complaints, Notification of Summons and Prosecution

9.0.1.     No environmental complaint was received in the reporting period.

9.0.2.     The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1

9.0.3.     Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.

Table 9.1    Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

May - December 2013

0

January 2014

0

Total

0

 

Table 9.2    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

0

0

0

Noise

0

0

0

Water

0

0

0

Waste

0

0

0

Total

0

0

0

10            conclusion

10.0.1.   The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

10.0.2.   The scheduled construction activities and the recommended mitigation measures for the coming month are listed in Table 10.1. The construction programmes of individual contracts are provided in Appendix 10.1.

Table 10.1  Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

Contract No.

Key Construction Works

Recommended Mitigation Measures

HK/2012/08

¡P         Concrete breaking

¡P         Stockpiling of fill materials

¡P         Culvert K diversion

¡P         Diaphragm wall preparation works

 

¡P         Dust control during dust generating works;

¡P         Open stockpiles of construction materials should be covered;

¡P         Implementation of proper noise pollution control ;and

¡P         Provision of protection to ensure no runoff out of site area or direct discharge into public drainage system.